Home Up Next

Change Form
Change Log

 

 

 

 

 

 

 

Project Management

horizontal rule

Change Form

Sample Document
When a project manager decides that the project is failing in some way, or the Sponsor identifies that the underlying business need has changed, it will be necessary to make a change to the project plan as defined in the PID.

The change should be documented in the Change Form and agreed with the Sponsor and Stakeholders at a Steering Committee meeting.

When should a "change" be formally managed?

The rule of thumb is "when it impacts more than one person or business unit". 

However, if a person takes on a change voluntarily but in doing so increases the time and/or cost of a task, the increased time will affect other people - so the change should be controlled and not just slipped through on the quiet.

The Process

Explain the change process to the project team, manager, sponsor and steering committee:
(a) to let them know how it impacts them
(b) to make sure they understand why it is important and the control it gives them 
(c) to make sure they know when they should use it 
When a change is identified make an entry in the log and complete a form. Completing the form makes sure that the significance and impact of the change has been considered and prompts analysis of the change and any necessary consultation actions. 
Hold a meeting with the sponsor to obtain their authority for the change and for any increase or reduction in time and cost.Changes that impact other people or business units are alterations to the original terms under which the project was commissioned. The sponsor may have to refer to the steering committee as well. 
Hold a meeting with any suppliers impacted to agree any changes in the contracts.

Change Form Contents

The change form describes the following:
a description of the nature of the change
priority of the change
the reason for the change
the implications for not making the change, including the related costs
preferred resolution
who is impacted and how
contractual implications

horizontal rule

Home ] Project Definition ] Project Failure ] Our Approach ] Project Management Cycle ] Project Organisation ] Roles Summary ] Project Governance ] Project Principles ] Project Timeline ] Benefits for You ] Contents ]

4-consulting 2-8 Millar Crescent, Edinburgh, EH10 5HW 
Tel 0131 447 4546  Fax 0131 447 8679
Copyright © 2002 4consulting